Friday, November 21, 2008

Construction Update


The sidewalk in the front of the church was poured on Wednesday. This sidewalk runs from the east end of our facilities to the worship center and our new front entrance.



There is still more work to be done, but we are beginning to see a real change in the front of the church.




The Facility Study Committee met with Paul Sanchez, our architect who is in charge of our building project on Wednesday night. We had a good meeting and learned that everything is going according to schedule for our new buildings. As you notice this morning, the new sidewalks in the front of the church have been poured. They are also new lights surrounding the worship center to light up the front and side parking lots. We were given the following schedule for the coming days.

· They are still deciding at this time whether to put down the asphalt in the front parking lot now or at the end of the project
· Construction on the foundations of two of new buildings will start in the middle of December.
· They will move the modular building over the Christmas holidays
· They will start work on the third foundation as soon as the modular building is moved.
· Foundations should be poured during the early part of January
· Completion date for the project is the end of March